20 men do a quarter part of a job in eight days. If the work needs to be completed in the next four days, how many more men are needed to achieve the target? a. 100 b. 120 c. 80 d. 50
Share
20 men do a quarter part of a job in eight days. If the work needs to be completed in the next four days, how many more men are needed to achieve the target? a. 100 b. 120 c. 80 d. 50
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
good night
Step-by-step explanation: