25 labourers can complete a building in 8 months. how many labourers will be required to construct another building of triple size as that of previous building in 10 months?
plz solve with steps
Share
25 labourers can complete a building in 8 months. how many labourers will be required to construct another building of triple size as that of previous building in 10 months?
plz solve with steps
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
=200 month
builders needed to complete work in 10 month =200÷10=20
20 labourers are required to do the work in 10 months