92 persons can complete a job in 38 days . In how many days will 46 persons complete the same job ?
Note - Kindly give step by step instructions or else you will be reported .
Share
92 persons can complete a job in 38 days . In how many days will 46 persons complete the same job ?
Note - Kindly give step by step instructions or else you will be reported .