A and B can finish a piece of work in 15 days and C in 20 days and while c and a in 30 days how long will it take to finish the work alone
Share
A and B can finish a piece of work in 15 days and C in 20 days and while c and a in 30 days how long will it take to finish the work alone
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Verified answer
[tex] \huge \tt \colorbox{magenta}{Answer}[/tex]
Ans ) ⇨60
A+B’s rate of work /day=1/20
B +C's rate of work /day=1/30
A-C 's rate of work/day=1/20–1/30=(3–2)/60= 1/60
2C-C=1/60
C=1/60
C will finish the work in 60 days
[tex] \huge \tt \colorbox{magenta}{Answer}[/tex]
[tex]\huge{{{\color{plum}{{ answer☃ :}}}}}[/tex]
Ans ) ⇨60
A+B’s rate of work /day=1/20
B +C's rate of work /day=1/30
A-C 's rate of work/day=1/20–1/30=(3–2)/60= 1/60
2C-C=1/60
C=1/60
C will finish the work in 60 day