A compack company required 35 machines to produce a given number of compacks in 60 days. How many machines would be required to produce the same number of compacks in 50 days?
Share
A compack company required 35 machines to produce a given number of compacks in 60 days. How many machines would be required to produce the same number of compacks in 50 days?
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
29
Step-by-step explanation:
35 machines are required to produce a given number of compacts in 60 days
let the number of machines to do the required work in 50 days be x
machines:days
35:60
x:50
60x = 35 × 50
x = 35 × 50/60
x = 29.1≈29
therefore, 29 machines will be required to the work in 50 days