A factory has 225 labourers who take care 72 days to complete the planned production . If the production has to be completed in 90 days , how many labourers will be required ? Please answer the question , also I want correct answer
Share
A factory has 225 labourers who take care 72 days to complete the planned production . If the production has to be completed in 90 days , how many labourers will be required ? Please answer the question , also I want correct answer
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
270 labourers
Step-by-step explanation:
72 days=225 labourers
1 day=225/72
1 day=3 labourers
90 days=3*90
90days=270
Answer:54
Step-by-step explanation:because first we need to see how many labourers will be required to do one days production so we need to do 225÷72 then we get answer as 3 .now we have to remove days of which we have to exceed days that is 90-72=18 so to find the lauberers just multiply 18×3=54
i hope you got your answer.please follow mw to get like this more explanations