A man undertakes to do a certain job in 32 days. He hires 12 men for the job. At the end of 8 days, only one fifth of the work is complete. How many extra men must be employed in order to complete the work in time?
Share
A man undertakes to do a certain job in 32 days. He hires 12 men for the job. At the end of 8 days, only one fifth of the work is complete. How many extra men must be employed in order to complete the work in time?
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Verified answer
Question:-
A man undertakes to do a certain job in 32 days. He hires 12 men for the job. At the end of 8 days, only one fifth of the work is complete. How many extra men must be employed in order to complete the work in time?
Answer:-
Analysis: 12 men 8 days = 1/5
So, 12 men 24 days = 3/5
So, 14 men 24 days = 1/5
1/5 + 3/5 + 1/5 = 1
He needs four extra mens.
Pardon..If wrong
~[tex] \: [/tex]
Answer:
Answer: 12 men 8 days = 1/5
Answer: 12 men 8 days = 1/5So, 12 men 24 days = 3/5
Answer: 12 men 8 days = 1/5So, 12 men 24 days = 3/5So, 14 men 24 days = 1/5
Answer: 12 men 8 days = 1/5So, 12 men 24 days = 3/5So, 14 men 24 days = 1/51/5 + 3/5 + 1/5 = 1
Answer: 12 men 8 days = 1/5So, 12 men 24 days = 3/5So, 14 men 24 days = 1/51/5 + 3/5 + 1/5 = 1He needs four extra mens.
Answer: 12 men 8 days = 1/5So, 12 men 24 days = 3/5So, 14 men 24 days = 1/51/5 + 3/5 + 1/5 = 1He needs four extra mens.4 extra men.
Answer: 12 men 8 days = 1/5So, 12 men 24 days = 3/5So, 14 men 24 days = 1/51/5 + 3/5 + 1/5 = 1He needs four extra mens.4 extra men.Pardon..If wrong