a worker is allowed 70 hours for a job actual time taken is 50 hours rate per hour is Rs 10. wage as per Halsey plan is
Share
a worker is allowed 70 hours for a job actual time taken is 50 hours rate per hour is Rs 10. wage as per Halsey plan is
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
Given in the problem is Standard hours 60
Basic wages is 10 per hour
Wages under Rowan scheme is 12 per hour. So difference 2 per hour is the incentive under Rowan.
Now Rowan incentive formula is (Actual hours / Std hours) (Time saved) (Basic Rate)
Let time saved be assumed to be x
Substituting in formula (x/60)(60-x)*10 = 2x
(x/60)(60-x) = 0.2x
x(60-x) = 12x
60x - x-squared = 12x
-x squared = -48x
x squared = 48x
x = 48 so Actual hours worked is 48
MARK ME BRAINLIEST
Verified answer
TOTAL WAGES EARNED DURING UNDER ROWAN PLAN 60x12= 720TOTAL BONUS EARNED DURING UNDER ROWAN PLAN 720-60X10=120
ACTUAL TIME SAVED FOR WORK= 120/10=12 HOURS
ACTUAL TIME TAKEN=60-12=48 HOURS
WAGES UNDER HALSEY PLAN (48X10+120*50/100)= 540/- ANS (B)