A is doing work in 30 days so everyday A is doing 1/30 part of work
B is doing work in 25 days,so everyday B is doing 1/25 part of work.
so in 10 days both will do 10 X(1/25 + 1/30 ) part of work.
=10/25 +10/30
=2/5 +1/3 =11/15 part of work done.
so work left is 1–11/15
=.4 / 15