For establishing a 1 MW generator using wind energy the land required will be about:
(A) 0.5 hectare (B) 6 hectare (C) 2 hectare (D) 4 hectare
Share
For establishing a 1 MW generator using wind energy the land required will be about:
(A) 0.5 hectare (B) 6 hectare (C) 2 hectare (D) 4 hectare
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
(C) 2 hectares
Explanation:
This is your Answer