If 20 workers can build a wal 36 m long in 15 days. The wal can be built by 30 workers in : (a) 24 days ( b) 18 days ( c) 15 days ( d ) 10 days
If 20 workers can build a wal 36 m long in 15 days. The wal can be built by 30 workers in : (a) 24 days ( b) 18 days ( c) 15 days ( d ) 10 days
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
20 workers can build a wall 36 m long in 15 days
1 worker can build a wall in 15x20x days
The wall can be built by 30 workers in X days
15x20 divided by 30
10 days