· If 24 men can do a piece of work in
24 days working 7 hours a day. In
how many days will 42 men finish the
same work, working 8 hours a day?
Share
· If 24 men can do a piece of work in
24 days working 7 hours a day. In
how many days will 42 men finish the
same work, working 8 hours a day?
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
Given,
24 men work 27 days 7 hours each day to complete a piece of work. Let a man can complete x piece of work in an hour.
i.e. power of a man = x (piece of work/hr)
Total work completed by 24 men in 27 days working 7 hours each day is,
total work = 24*x*27*7
now,
Same total work completed by 14 men in y days working 9 hours each day is now given by
total work = 14*x*(y)*9
observe 24*x*27*7 = 14*x*(y)*9
Thus, the equation gives y = 36 days.
So, 14 men takes 36 days to complete the piece of work working 9 hours each day.