if 3 men take 12 days to complete a job how much time will 4 men take with same consistency ......answer with complete method.
Share
if 3 men take 12 days to complete a job how much time will 4 men take with same consistency ......answer with complete method.
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Step-by-step explanation:
no.of men-3
no.of days-12
no.of days 1 man take to complete job-12÷3=4 days
no.of days 4 men to take complete job-4×4=8 days
so 4 men take 8 days to complete job.