. If it takes 4 people 4 days to dig a
hole, how long does it take 2 people
to dig a half hole ?
Share
. If it takes 4 people 4 days to dig a
hole, how long does it take 2 people
to dig a half hole ?
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer:
Two days.
It's obvious.
Please mark as brainliest.
Answer:
The total input required to dig the original hole is 4 people x 4 days, so 16 man-days. Half that input is 8 man-days. Divide that by the 2 people digging, and you get 4 days...